Work on the Red Wing Pedestrian Bridge continues.
The contractor is continuing with the ornamental railing installation and expects at least another week to fully complete.
Additionally, final preparations for the new concrete deck pour are being completed. The deck is still scheduled to be poured on today by means of a concrete pumper truck in coordination with CP rail.
The trail paving is scheduled to be completed this week. Immediately after the paving, the embankment is scheduled to be graded with new topsoil and seeded.
Overall, the project is on schedule for a bridge completion and opening by end of September.