Work continues on Old West Main Street in Red Wing.
The Contractor has successfully installed the new sanitary sewer and watermain up to the pavement removal limits halfway between Jefferson and Washington.
Starting first thing this week the Contractor plans to remove the rest of the pavement up to the east side of Jefferson Street. Immediately following the pavement removal, the Contractor plans to continue with the new sanitary sewer from current manhole mid-block to a new manhole on the east side of Jefferson.
Following the sanitary sewer, the Contractor plans to continue with the new watermain up to the east side of Jefferson.
The intersection of Jefferson St will remain open at least another week, however, it is possible that the Contractor will be looking to close the intersection to continue progressing with the project sometime the week of May 9th.