Cannon Valley Trail Update
- Greg Taylor
- Aug 5
- 1 min read

Great news on Project One on the Cannon Valley Trail.
The trail has reopened from Mile 13.5 to Mile 15.5, including Cannon Bottom Road Access.
A few remaining tasks still need to be completed before Project One is fully finished, including fence installation at Mile 14, bridge removal at Mile 14.5, and a box culvert at Mile 15.
When work begins, Mile 14 to Mile 15.5 will temporarily close again.
Also a reminder that Project Two — Bridge & Asphalt Replacement from Mile 15.5 to Mile 19.7 — is underway.
That section will be closed to trail users through June 2027.
Welch Station Access, Cannon Falls Access, and Cannon Bottom Road Access will all remain available.
For maps and more details, go to cannonvalleytrail.com.